January 2014 to May 2014

Collections move off of the first floor of Bostock into other locations
Collections in other parts of the building move to allow room for Bostock first floor collections

May 2014

Bostock entrance and first floor closes
Furniture and equipment moves off of the first floor of Bostock into other locations
Perkins front entrance closes due to Rubenstein Library renovation
Perkins Research Desk moves to Perkins side entrance and becomes main Service Desk

June 2014

Construction begins on Bostock first floor to create the Research Commons

Summer 2014

Collections move in several locations in Perkins Library to allow for study space

November 2014

Construction finishes on Bostock first floor

November 2014 to December 2014

With construction complete, the Research Commons will be open for use as we prepare for our grand opening in January

January 2015

Research Commons grand opening